Such excitment each day, as I walk the building site and see the classrooms coming to life and nearly fully complete for our Year 1 students and The ARTS room.
Work has progressed significantly on the ground floor teaching spaces, with painting and floor coverings completed, with electrical fit off, testing and commissioning to be completed this week. Electrical/Mechanical Engineers were on site yesterday doing their inspection.
Joinery installation is planned for the remainder of this week. Minor touch-up painting and sealing to be done early next week. The completion of the external works, landscaping etc is ongoing.
Anticipated occupation is in sight so that the teaching and learning can commence in these spaces from Monday 21 February 2022.
Work continues on Administration with all plastering and glazing complete. Wall and floor tiling has commenced and toilet partition walls and doors are in. Floor prep is to commence next week, along with painting. Expected practical completion for this portion is March 2022. I will continue to keep you updated. In the meantime enjoy the photo montage.